Nabhraj Builders And Developers Pvt Ltd
Deedo IDDD-W1TAOf 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
2 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nabhraj Trilok HeightsP51500032020 | Aurangabad | Active | 31 Dec 2026 | 31 Dec 2029 | +36 mo |
| Nabhraj TrimurtiP51500047311 | Aurangabad (M Corp.) | Certificate Signed | 25 Feb 2025 | 25 Feb 2025 | On date |
| Nabhraj NikunjP51500049264 | Kubhephal | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Nabhraj RYAN BUSINESS HUBP51500052587 | Aurangabad (M Corp.) | Active | 31 Dec 2030 | — | On date |
| Nabhraj SymphonyPM1040002601552 | Itkheda | Certificate Signed | 31 Dec 2032 | 31 Dec 2032 | On date |
| Nabhraj Trilok Heights MHADAPR1041012602140 | Shahanur Wadi | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
Nabhraj Builders And Developers Pvt Ltd, in questions
Does Nabhraj Builders And Developers Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Nabhraj Builders And Developers Pvt Ltd registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 1 completed on MahaRERA.
Does Nabhraj Builders And Developers Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.