Mrunal Avinash Tarpe

Deedo IDDD-A711

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay8 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sitaram ApartmentP50500078537Nagpur (M Corp.)Certificate Signed31 Mar 202631 Jul 2026+8 mo*

Mrunal Avinash Tarpe, in questions

Does Mrunal Avinash Tarpe finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.

How many projects has Mrunal Avinash Tarpe registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Mrunal Avinash Tarpe have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology