Monish Bharat Bahal
Deedo IDDD-ZW6XOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 9 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bharat Height ApartmentP50500026514 | Nagpur (M Corp.) | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | +14 mo* |
| Bharat ResidencyP50500055971 | Nagpur (M Corp.) | Certificate Signed | 20 Mar 2030 | 20 Jul 2030 | +4 mo |
Monish Bharat Bahal, in questions
Does Monish Bharat Bahal finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 9 mo late. Across Maharashtra, 73% kept their date.
How many projects has Monish Bharat Bahal registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Monish Bharat Bahal have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.