Mohini Sheltors Private Limited
Deedo IDDD-52X6Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mohini CastleP51800005492 | Andheri | Certificate Signed | 30 Jun 2021 | 30 Jun 2023 | +24 mo |
| Mohini TowerP51800006731 | Andheri | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
Mohini Sheltors Private Limited, in questions
Does Mohini Sheltors Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has Mohini Sheltors Private Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Mohini Sheltors Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.