Individual promoter · first RERA registration 2020

Mohan Vasudeo Hundare

Deedo IDDD-5EZ2

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Omkar PlazaP52900025444Kudal (Ct)Certificate Signed30 Jun 202430 Jun 2024On date
Audumbar PlazaP52900032635Kudal (Ct)Certificate Signed31 Dec 202431 Dec 2024On date
Shree Laxmi PlazzaP52900054099Kudal (Ct)Certificate Signed30 Jun 202730 Oct 2027+4 mo

Mohan Vasudeo Hundare, in questions

Does Mohan Vasudeo Hundare finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Mohan Vasudeo Hundare registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Mohan Vasudeo Hundare have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology