Millennium Developers
Deedo IDDD-RV9ZOf 6 registrations whose promised date has arrived, 6 kept it (100%).
Delivery record
2 of 8 registrations with dates moved or missed their RERA date · months late against the original promise
8 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| DivineP52100000055 | Borhadewadi | Completed | 1 Aug 2018 | — | On date |
| AcropolisP52100000088 | Wakad | Certificate Signed | 15 Jan 2020 | 15 Jan 2020 | On date |
| AcropolisP52100015821 | Wakad | Certificate Signed | 15 Apr 2022 | 15 Apr 2022 | On date |
| Millennium ManorP52100021632 | Chikhali | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Millennium PacificP52100027204 | Tathwade | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Millennium AtlasP52100035007 | Tathwade | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | On date |
| Millennium AmaraP52100052838 | Mamurdi | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
| Millennium FalconP52100053875 | Tathwade | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Millennium Developers, in questions
Does Millennium Developers finish projects on time?
Of 6 MahaRERA registrations whose promised completion date has arrived, 6 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Millennium Developers registered with MahaRERA?
7 projects under 8 MahaRERA registrations; 6 completed on MahaRERA.
Does Millennium Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.