Individual promoter · first RERA registration 2019

Milankumar Vasantsingh Pardeshi

Deedo IDDD-72XV

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 5 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay5 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shree Samarth AayodhyaP52100022243VitthalvadiCertificate Signed30 Sep 202028 Feb 2021+5 mo

Milankumar Vasantsingh Pardeshi, in questions

Does Milankumar Vasantsingh Pardeshi finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.

How many projects has Milankumar Vasantsingh Pardeshi registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Milankumar Vasantsingh Pardeshi have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology