Metrocity Projects
Deedo IDDD-TYK8Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Metrocity 1P50500026206 | Shankarpur | Certificate Signed | 31 Dec 2020 | 30 Jun 2022 | +18 mo |
| Metrocity-3P50500027456 | Nagpur (M Corp.) | Certificate Signed | 28 Feb 2021 | 28 Aug 2022 | +18 mo |
| DestinyP50500045564 | Nagpur (M Corp.) | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Metrocity-VP50500048575 | Nagpur (Rural) | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | On date |
| MetrocityP50500050247 | Gawasi Manapur | Completed | 31 Dec 2028 | — | On date |
| MetrocityP50500055243 | Gawasi Manapur | Completed | 31 Dec 2029 | — | On date |
Metrocity Projects, in questions
Does Metrocity Projects finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Metrocity Projects registered with MahaRERA?
5 projects under 6 MahaRERA registrations; 6 completed on MahaRERA.
Does Metrocity Projects have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.