Metrocity Projects
Company or firm · 5 projects · 6 MahaRERA registrations · 2 reported completed
Projects56 RERA registrations
Completed2as reported on MahaRERA project pages
Kept RERA date50%2 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Metrocity 1P50500026206 | Shankarpur | 2020 | Not reported | 31 Dec 2020 | 30 Jun 2022 | +18 months |
| Metrocity-3P50500027456 | Nagpur (M Corp.) | 2020 | Not reported | 28 Feb 2021 | 28 Aug 2022 | +18 months |
| DestinyP50500045564 | Nagpur (M Corp.) | 2022 | Not reported | 31 Dec 2024 | — | On date |
| Metrocity-VP50500048575 | Nagpur (Rural) | 2023 | Not reported | 31 Dec 2023 | — | On date |
| MetrocityP50500050247 | Gawasi Manapur | 2023 | Completed | 31 Dec 2028 | — | On date |
| MetrocityP50500055243 | Gawasi Manapur | 2024 | Completed | 31 Dec 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Metrocity 1 (P50500026206).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology