Company or firm · first RERA registration 2024

Mangalmurti Vinay Unique Realtors

Deedo IDDD-KP1W

None of 3 registrations has reached its promised completion date yet.

Projects13 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Super Homez HarmonyP99000077447DongreCertificate Signed30 Jun 202730 Oct 2027+4 mo
Super Homez HarmonyPR1241012502347DongreCertificate Signed30 Jun 202830 Oct 2028+4 mo
Super Homez HarmonyPR1242022602022DongreCertificate Signed31 Dec 202931 Dec 2029On date

Mangalmurti Vinay Unique Realtors, in questions

Does Mangalmurti Vinay Unique Realtors finish projects on time?

None of its 3 MahaRERA registrations has reached its promised completion date yet.

How many projects has Mangalmurti Vinay Unique Realtors registered with MahaRERA?

1 project under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Mangalmurti Vinay Unique Realtors have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology