Deedo IDDD-KP1WNone of 3 registrations has reached its promised completion date yet.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Super Homez HarmonyP99000077447 | Dongre | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Super Homez HarmonyPR1241012502347 | Dongre | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
| Super Homez HarmonyPR1242022602022 | Dongre | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
Mangalmurti Vinay Unique Realtors, in questions
Does Mangalmurti Vinay Unique Realtors finish projects on time?
None of its 3 MahaRERA registrations has reached its promised completion date yet.
How many projects has Mangalmurti Vinay Unique Realtors registered with MahaRERA?
1 project under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Mangalmurti Vinay Unique Realtors have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.