Majestique Empire Llp
Deedo IDDD-0Y1HOf 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 7 mo late.
Delivery record
4 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Majestique MarbellaP52100025697 | Kharadi | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
| Majestique MarbellaP52100030349 | Kharadi | Certificate Signed | 31 Dec 2024 | 30 Sep 2025 | +23 mo* |
| Majestique MarbellaP52100030934 | Kharadi | Certificate Signed | 31 Dec 2024 | 30 Sep 2025 | +9 mo |
| Majestique MarbellaP52100031184 | Kharadi | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Majestique MarbellaP52100032450 | Kharadi | Completed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Majestique Marbella Phase VIP52100051012 | Kharadi | Certificate Signed | 30 Apr 2027 | 30 Aug 2027 | +4 mo |
Majestique Empire Llp, in questions
Does Majestique Empire Llp finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 7 mo late. Across Maharashtra, 73% kept their date.
How many projects has Majestique Empire Llp registered with MahaRERA?
2 projects under 6 MahaRERA registrations; 3 completed on MahaRERA.
Does Majestique Empire Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.