Maheshwari Developers
Deedo IDDD-9NQ4Of 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 49 mo late.
Delivery record
4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AxisaP52100003153 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Mar 2019 | 15 Jun 2023 | +51 mo |
| Suvarna NagariP52100005673 | Charholi | Certificate Signed | 1 Dec 2022 | 1 Dec 2023 | +47 mo* |
| Suvarna AlayP52100006825 | Charholi Kh | Certificate Signed | 31 Dec 2018 | 30 Dec 2026 | +96 mo |
| Axisa D WingP52100024645 | Kivale | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | +32 mo* |
| Suvarna Nagari Ph-2P52100034256 | Charholi Kh | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Maheshwari Developers, in questions
Does Maheshwari Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 49 mo late. Across Maharashtra, 73% kept their date.
How many projects has Maheshwari Developers registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 1 completed on MahaRERA.
Does Maheshwari Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.