Maheshwaram Associates
Deedo IDDD-Q3Y3Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 5 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Maheshwaram MajesticP52100032195 | Ravet | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
| Maheshwaram Vrinda Phase-1P52100078935 | Ravet | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Maheshwaram Associates, in questions
Does Maheshwaram Associates finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Maheshwaram Associates registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Maheshwaram Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.