Maheshwar Enterprises
Deedo IDDD-F7SYOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shivram ResidencyP51600049208 | Nashik (M Corp.) | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Shivganga HillsP51600050161 | Nashik (M Corp.) | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Shivram Residency 2P51600052590 | Pathardi | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Shivanjali AvenuePR1220002601047 | Pathardi | Certificate Signed | 31 Oct 2028 | 28 Feb 2029 | +4 mo |
Maheshwar Enterprises, in questions
Does Maheshwar Enterprises finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Maheshwar Enterprises registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Maheshwar Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.