Skip to content
Individual promoter · first RERA registration 2023

Mahesh Wamanrao Chute

Deedo IDDD-SCBR

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
SymphonyP50500052682Nagpur (M Corp.)Certificate Signed1 Aug 20271 Aug 2027On date

Mahesh Wamanrao Chute, in questions

Does Mahesh Wamanrao Chute finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Mahesh Wamanrao Chute registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Mahesh Wamanrao Chute have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology