Deedo IDDD-BQ8FOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Quarterly progress report not filed | Ankit FionaQuarterly progress report not filed: ANKIT FIONA PHASE 2 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ankit FionaP52000012190 | Bhuwaneshwar (Ct) | Certificate Signed | 31 Dec 2018 | 30 Oct 2020 | +22 mo |
| Ankit FionaP52000018126 | Bhuwaneshwar (Ct) | Certificate Signed | 30 Jun 2021 | 31 Dec 2026 | +66 mo |
Mahesh Suhas Padalkar, in questions
Does Mahesh Suhas Padalkar finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.
How many projects has Mahesh Suhas Padalkar registered with MahaRERA?
1 project under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Mahesh Suhas Padalkar have MahaRERA regulatory cases?
1 regulatory case name its registrations.