Individual promoter · first RERA registration 2017

Mahesh Suhas Padalkar

Deedo IDDD-BQ8F

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay44 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Quarterly progress report not filedAnkit FionaQuarterly progress report not filed: ANKIT FIONA PHASE 2Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Ankit FionaP52000012190Bhuwaneshwar (Ct)Certificate Signed31 Dec 201830 Oct 2020+22 mo
Ankit FionaP52000018126Bhuwaneshwar (Ct)Certificate Signed30 Jun 202131 Dec 2026+66 mo

Mahesh Suhas Padalkar, in questions

Does Mahesh Suhas Padalkar finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.

How many projects has Mahesh Suhas Padalkar registered with MahaRERA?

1 project under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Mahesh Suhas Padalkar have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology