Mahavir Properties
Deedo IDDD-3KFZOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vivaan HeightsP99000009840 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Kanti RegencyP99000010163 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
Mahavir Properties, in questions
Does Mahavir Properties finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has Mahavir Properties registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Mahavir Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.