Company or firm · first RERA registration 2018

Mahavir Developers

Deedo IDDD-5CWE

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Patel ManzilP52000016227UlaweCertificate Signed30 Dec 202130 Dec 2021On date
Patel KunjP52000022129UlaweCertificate Signed30 May 202230 May 2022On date
Patel AuraP52000077724UlaweCertificate Signed31 Aug 202631 Dec 2026+4 mo

Mahavir Developers, in questions

Does Mahavir Developers finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Mahavir Developers registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Mahavir Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology