Maharshee Builders
Deedo IDDD-1KB3Of 4 registrations whose promised date has arrived, 4 kept it (100%).
Delivery record
1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Maharshee ManoharP50500015440 | Nagpur (M Corp.) | Completed | 28 Feb 2021 | — | On date |
| DattatreyP50500020916 | Nagpur (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| AgastiP50500021601 | Nagpur (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Maharshee SquareP50500030042 | Besa | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Nakshatra ApartmentP50500053384 | Beltarodi | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
Maharshee Builders, in questions
Does Maharshee Builders finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Maharshee Builders registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 4 completed on MahaRERA.
Does Maharshee Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
