Company or firm · first RERA registration 2021

Mahalaxmi Infracon

Deedo IDDD-922Z

Of 7 registrations whose promised date has arrived, 7 kept it (100%).

Projects1314 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 14 registrations with dates moved or missed their RERA date · months late against the original promise

14 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mahalaxmi Nagar - 16 Sactor 2P50500027971KothewadaCertificate Signed10 Jul 202410 Jul 2024On date
Mahalaxmi Nagar - 16 Sactor 3P50500028000KothewadaCertificate Signed10 Jul 202410 Jul 2024On date
Mahalaxmi Nagar - 16P50500028015Nagpur (Rural)Certificate Signed10 Jul 202410 Jul 2024On date
Mahalaxmi Nagar 21P50500032406ShankarpurCertificate Signed25 Dec 202525 Dec 2025On date
Mahalaxmi Nagar - 19P50500032476Nagpur (Rural)Certificate Signed5 Dec 20245 Dec 2024On date
Mahalaxmi Nagar - 23 Sector - 2P50500047202JamthaCertificate Signed14 May 202514 May 2025On date
Mahalaxmi Nagar 26P50500047841KothewadaCertificate Signed2 Nov 20262 Nov 2026On date
Mahalaxmi Nagar 35P50500054265KothewadaCertificate Signed20 Dec 202820 Dec 2028On date
Mahalaxmi NagarP50500054986KothewadaCertificate Signed2 Jan 20292 Jan 2029On date
Mahalaxmi NagarP50500055362KothewadaCertificate Signed20 Jan 202920 Jan 2029On date
Mahalaxmi Nagar 41 Sector - 1P50500077213ShivmadkaCertificate Signed15 Jul 202915 Nov 2029+4 mo
Mahalaxmi Nagar 41PP1190002400092GumgaonCertificate Signed13 Sep 202913 Jan 2030+4 mo
Mahalaxmi Nagar - 45 : Sector 2PP1190002501287SumthanaCertificate Signed30 Aug 203030 Dec 2030+4 mo
MAHALAXMI NAGAR 41 : Sector-2PP1190002601470ShivmadkaCertificate Signed31 Jul 203131 Jul 2031On date
Show all 14 registrationsShow fewer

Mahalaxmi Infracon, in questions

Does Mahalaxmi Infracon finish projects on time?

Of 7 MahaRERA registrations whose promised completion date has arrived, 7 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Mahalaxmi Infracon registered with MahaRERA?

13 projects under 14 MahaRERA registrations; 10 completed on MahaRERA.

Does Mahalaxmi Infracon have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology