Mahalaxmi Infra
Deedo IDDD-DMNJOf 7 registrations whose promised date has arrived, 7 kept it (100%).
Delivery record
None of 7 registrations with dates has moved or missed its RERA date
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mahalaxmi Nagar 1P50500001839 | Jamtha | Completed | 31 Jul 2018 | — | On date |
| Shivthirth Nagar 2P50500001948 | Gotal Panjari | Completed | 31 Jul 2018 | — | On date |
| Mahalaxmi NagarP50500002993 | Jamtha | Certificate Signed | 31 Jul 2018 | 31 Jul 2018 | On date |
| Mahalaxmi NagarP50500003449 | Jamtha | Completed | 31 Jul 2018 | — | On date |
| Nakshtra 3P50500003529 | Wagdara (536084) | Completed | 31 Jul 2018 | — | On date |
| Mahalaxmi Nagar 5 - Survey No 9P50500016892 | Jamtha | Completed | 29 Feb 2020 | — | On date |
| Mahalaxmi Nagar - 9P50500020050 | Waroda | Certificate Signed | 1 Jun 2024 | 1 Jun 2024 | On date |
Mahalaxmi Infra, in questions
Does Mahalaxmi Infra finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 7 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Mahalaxmi Infra registered with MahaRERA?
6 projects under 7 MahaRERA registrations; 7 completed on MahaRERA.
Does Mahalaxmi Infra have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.