Madhhu Daulatrao Patil
Deedo IDDD-CH2ROf 2 registrations whose promised date has arrived, 2 kept it (100%).
Delivery record
None of 2 registrations with dates has moved or missed its RERA date
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| NageshwarP52000006769 | Taloje Panchnad | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| BhimashankarP52000011874 | Taloje Panchnad | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
Madhhu Daulatrao Patil, in questions
Does Madhhu Daulatrao Patil finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Madhhu Daulatrao Patil registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Madhhu Daulatrao Patil have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.