Company or firm · first RERA registration 2017
Lushlife Real Estate Llp
Deedo IDDD-VARTOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 15 mo late — longer than Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay15 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| ImperoP52100013409 | Ouatade Handewadi | Certificate Signed | 30 Sep 2022 | 31 Dec 2023 | +15 mo |
| CentroP52100014734 | Ouatade Handewadi | Certificate Signed | 30 Sep 2022 | 31 Dec 2024 | +27 mo |
| Lushlife Impero Building CPR1261012503001 | Ouatade Handewadi | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology