Company or firm · first RERA registration 2017
Lokhandwala Kataria Construction Private Limited
Deedo IDDD-CVDGNone of 1 registration has reached its promised completion date yet.
Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | MinervaRegulatory order: PROJECT NAME:MINERVA (Regulatory Case No. 165 of 2024) dated 13 March 2024. | 13 Mar 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| MinervaP51900008204 | Lower Parel | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Lokhandwala Kataria Construction Private Limited, in questions
Does Lokhandwala Kataria Construction Private Limited finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Lokhandwala Kataria Construction Private Limited registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Lokhandwala Kataria Construction Private Limited have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology