Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 85 mo — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay85 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Lobpsons & Tania Builders developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 1 moved past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Lobpsons And Tania IndustriesP99000008005SativaliCertificate Signed1 May 201826 Jun 2025+85 mo