Lavim Developers Pvt Ltd
Deedo IDDD-SE7POf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Broadway - Brooklyn, Manhattan and EWSP52100016356 | Wakad | Certificate Signed | 1 Jun 2024 | 1 Jun 2024 | +29 mo* |
| Forest Trails Athashri B3P52100077686 | Bhugaon | Certificate Signed | 30 Sep 2029 | 30 Jan 2030 | +4 mo |
Lavim Developers Pvt Ltd, in questions
Does Lavim Developers Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Lavim Developers Pvt Ltd registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Lavim Developers Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.