Lalita Dharamchand Phulfagar

Deedo IDDD-1FQ8

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects13 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
1 SadabaugP52100076649ShirurCertificate Signed30 Sep 202630 Jan 2027+4 mo
1 SadabaugP52100077021ShirurCertificate Signed30 Sep 202630 Jan 2027+4 mo
1 SadabaugP52100077024ShirurCertificate Signed30 Sep 202630 Jan 2027+4 mo

Lalita Dharamchand Phulfagar, in questions

Does Lalita Dharamchand Phulfagar finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Lalita Dharamchand Phulfagar registered with MahaRERA?

1 project under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Lalita Dharamchand Phulfagar have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology