Lalani Constructions Private Limited
Deedo IDDD-HN3HOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 32 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| LalanibusinessparkP51800033063 | Bandra | Certificate Signed | 31 Mar 2024 | 31 Mar 2026 | +32 mo* |
| Lalani GoodwillP51800079065 | Kondivita | Certificate Signed | 30 Jun 2028 | 30 Jun 2028 | On date |
Lalani Constructions Private Limited, in questions
Does Lalani Constructions Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 32 mo late. Across Maharashtra, 73% kept their date.
How many projects has Lalani Constructions Private Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Lalani Constructions Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
