Company or firm · first RERA registration 2022

Lalani Constructions Private Limited

Deedo IDDD-HN3H

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 32 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay32 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
LalanibusinessparkP51800033063BandraCertificate Signed31 Mar 202431 Mar 2026+32 mo*
Lalani GoodwillP51800079065KondivitaCertificate Signed30 Jun 202830 Jun 2028On date

Lalani Constructions Private Limited, in questions

Does Lalani Constructions Private Limited finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 32 mo late. Across Maharashtra, 73% kept their date.

How many projects has Lalani Constructions Private Limited registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Lalani Constructions Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology