L&T Realty Properties Limited
Deedo IDDD-FFADNone of 6 registrations has reached its promised completion date yet.
Delivery record
3 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| L And T Seawoods - Opal At West SquareP51700045794 | Navi Mumbai (M Corp.) | Certificate Signed | 31 Jan 2027 | 31 Jan 2027 | On date |
| L And T Seawoods - Amber At West SquareP51700045795 | Navi Mumbai (M Corp.) | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| L And T Seawoods - Coral At West SquareP51700045802 | Navi Mumbai (M Corp.) | Certificate Signed | 31 Jan 2027 | 31 May 2027 | +4 mo |
| L AND T SEAWOODS - West Manor Tower A and BP51700056254 | Navi Mumbai (M Corp.) | Active | 31 Oct 2027 | — | On date |
| The Villas at Seawoods ResidencesPR1330002500464 | Others | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
| L And T Seawoods - Topaz At West SquarePR1330002500693 | Others | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
L&T Realty Properties Limited, in questions
Does L&T Realty Properties Limited finish projects on time?
None of its 6 MahaRERA registrations has reached its promised completion date yet.
How many projects has L&T Realty Properties Limited registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 1 completed on MahaRERA.
Does L&T Realty Properties Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.