Kunal Spaces Pvt Ltd

Deedo IDDD-4WTM

Of 3 registrations whose promised date has arrived, 3 kept it (100%).

Projects13 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 3 registrations with dates has moved or missed its RERA date

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kunal AspireeP52100001814BanerCertificate Signed31 Dec 201831 Dec 2018On date
Kunal AspireeP52100002540BanerCertificate Signed30 Jun 202230 Jun 2022On date
Kunal AspireeP52100027175BanerCertificate Signed30 Jun 202530 Jun 2025On date

Kunal Spaces Pvt Ltd, in questions

Does Kunal Spaces Pvt Ltd finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Kunal Spaces Pvt Ltd registered with MahaRERA?

1 project under 3 MahaRERA registrations; 3 completed on MahaRERA.

Does Kunal Spaces Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology