Individual promoter · first RERA registration 2017
Kunal Avinash Kumthekar
Deedo IDDD-63QDOf 6 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 63 mo late.
Projects26 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay63 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases4no insolvency
Delivery record
6 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Kenisha Holiday HomesDeregistered: KENISHA HOLIDAY HOMES - CLUSTER O | Not on record |
| Deregistered | Kenisha Holiday HomesDeregistered: KENISHA HOLIDAY HOMES CLUSTER H AND I | Not on record |
| Deregistered | Kenisha Holiday HomesDeregistered: KENISHA HOLIDAY HOMES CLUSTER H AND I | Not on record |
| Deregistered | Kenisha Holiday HomesDeregistered: KENISHA HOLIDAY HOMES - CLUSTER N | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kenisha Holiday Homes - Cluster E-J-KP52000000966 | Pawasalawadi | Certificate Signed | 31 Dec 2018 | 30 Jun 2024 | +66 mo |
| Kenisha Holiday HomesP52000012932 | Pawasalawadi | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +17 mo* |
| Kenisha Holiday HomesP52000013220 | Pawasalawadi | Certificate Signed | 30 Jun 2019 | 30 Jun 2024 | +60 mo |
| Kenisha Holiday HomesP52000014752 | Pawasalawadi | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | +59 mo* |
| Kenisha Holiday HomesP52000014764 | Pawasalawadi | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | +71 mo* |
| Kenisha Holiday HomesP52000016055 | Pawasalawadi | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | +71 mo* |
Kunal Avinash Kumthekar, in questions
Does Kunal Avinash Kumthekar finish projects on time?
Of 6 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 63 mo late. Across Maharashtra, 73% kept their date.
How many projects has Kunal Avinash Kumthekar registered with MahaRERA?
2 projects under 6 MahaRERA registrations; 2 completed on MahaRERA.
Does Kunal Avinash Kumthekar have MahaRERA regulatory cases?
4 regulatory cases name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology