Company or firm · first RERA registration 2017
Kumar Construction And Properties Pvt Ltd
Deedo IDDD-18BGOf 15 registrations whose promised date has arrived, 14 kept it (93%). The rest ran a median 5 mo late — longer than Maharashtra's 4 mo.
Projects1616 RERA registrations
Kept RERA date93%Maharashtra: 73%
Median delay5 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 16 ran past the RERA date
Months late against the original RERA promise, per registration
Show all 16 registrations
16 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Selena BP52100000252 | Pashan | Certificate Signed | 30 Mar 2019 | 30 Mar 2019 | On date |
| Princeville - B3 and C1P52100000755 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 May 2019 | 31 May 2019 | On date |
| PiccadillyP52100003854 | Wakad | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Primus - AP52100004518 | Hadapsar | Certificate Signed | 30 Jun 2021 | 30 Dec 2021 | +6 mo |
| Princeville - B4 and B5P52100015685 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 28 Aug 2022 | 28 Aug 2022 | On date |
| Kumar Palmgrove A6P52100016606 | Kondhwa Bk | Certificate Signed | 30 Apr 2024 | 30 Apr 2024 | On date |
| Kumar Pebble Park Anand 3- A1 Core3P52100016951 | Hadapsar | Certificate Signed | 30 Apr 2023 | 30 Apr 2023 | On date |
| Kumar Pebble Park Khushi 2- D2P52100020421 | Hadapsar | Certificate Signed | 1 Apr 2024 | 1 Apr 2024 | On date |
| Kumar Piccadilly E BuildingP52100022179 | Wakad | Certificate Signed | 28 Aug 2023 | 28 Aug 2023 | On date |
| Kumar Piccadilly Commercial BuildingP52100022516 | Wakad | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | On date |
| Kumar Selena A BuildingP52100023773 | Pashan | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Kumar Piccadilly F BuildingP52100024439 | Wakad | Certificate Signed | 30 Jan 2025 | 30 Jan 2025 | On date |
| Kumar Papillon A3 BuildingP52100024454 | Pashan | Certificate Signed | 30 Jan 2025 | 30 Jan 2025 | On date |
| Kumar PiccadillyP52100029950 | Wakad | Certificate Signed | 31 May 2025 | 31 May 2025 | On date |
| Kumar Primrose C BuildingP52100030114 | Kharadi | Certificate Signed | 31 Dec 2022 | 31 Dec 2022 | On date |
| Kumar Padmalaya B04 & B05PR1260002501766 | Aundh | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
Show all 16 registrationsShow fewer
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology