Krps Properties

Deedo IDDD-BN5X

None of 2 registrations has reached its promised completion date yet.

Projects12 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Adinath AanganP51500077736DevlaiCertificate Signed15 Aug 202715 Dec 2027+4 mo
Adinath AanganP51500077794DevlaiCertificate Signed15 Aug 202715 Dec 2027+4 mo

Krps Properties, in questions

Does Krps Properties finish projects on time?

None of its 2 MahaRERA registrations has reached its promised completion date yet.

How many projects has Krps Properties registered with MahaRERA?

1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Krps Properties have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology