Kothari Construction Co
Deedo IDDD-0W1BOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 30 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Apeksha ComplexP99000009883 | Vasaivirar City (M Corp) | Certificate Signed | 30 Dec 2022 | 30 Dec 2026 | +48 mo |
| Apeksha Shopping CentreP99000010073 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2017 | 30 Dec 2018 | +12 mo |
Kothari Construction Co, in questions
Does Kothari Construction Co finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 30 mo late. Across Maharashtra, 73% kept their date.
How many projects has Kothari Construction Co registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Kothari Construction Co have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.