Kotak Sons
Deedo IDDD-VZQCOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 42 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Golden EyeP99000003915 | Shirgaon | Certificate Signed | 28 Feb 2019 | 28 Feb 2019 | On date |
| Golden Eye Phase IIIP99000014416 | Shirgaon | Certificate Signed | 28 Feb 2019 | 28 Feb 2020 | +12 mo |
| Kotak RoyaleP99000017141 | Palghar | Certificate Signed | 1 Dec 2020 | 31 May 2025 | +71 mo* |
Kotak Sons, in questions
Does Kotak Sons finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.
How many projects has Kotak Sons registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Kotak Sons have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.