Kolte-Patil Integrated Townships Limited

Deedo IDDD-7JV2

Of 11 registrations whose promised date has arrived, 6 kept it (55%). The rest ran a median 23 mo late.

Projects912 RERA registrations
Kept RERA date55%Maharashtra: 73%
Median delay23 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

5 of 12 registrations with dates moved or missed their RERA date · months late against the original promise

12 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Life Republic Sector R2 - 2nd AvenueP52100002682MarunjiCertificate Signed31 Mar 201930 Sep 2020+18 mo
Life Republic Sector R3 3rd AvenueP52100007511JambeCertificate Signed31 Dec 201931 Dec 2019On date
Life Republic Sector R16 - 16th AvenueP52100009640JambeCertificate Signed30 Dec 202230 Dec 2022On date
Life Republic Sector R3 3rd AvenueP52100016987JambeCertificate Signed30 Dec 202230 Dec 2022On date
Life Republic Sector R9-Oro AvenueP52100017116JambeCertificate Signed31 Jul 202431 Jul 2024On date
Life Republic Sector R16 16th Avenue ArezoP52100018539JambeCertificate Signed30 Dec 202330 Dec 2023On date
Life Republic Sector R7- 7th Avenue- i TowersP52100022154MulshiCertificate Signed30 Dec 202430 Dec 2024+23 mo*
Life Republic - Sector R 17 B - 17 B Avenue - NoraP52100022278JambeCertificate Signed30 Mar 202230 Mar 2022On date
Life Republic Sector R16 16th Avenue ArezoP52100023317JambeCertificate Signed30 Dec 202431 Dec 2024+23 mo*
Life Republic Sector C1 - City ElanzaP52100026426JambeCertificate Signed31 Jul 202331 Jul 2023+40 mo*
Life Republic Sector R16 16th Avenue ArezoP52100031799JambeCertificate Signed31 Oct 202531 Oct 2025+13 mo*
Life Republic Sector R13/13th Avenue/Aros/Phase-IIP52100054550NereCertificate Signed30 Jun 202830 Jun 2028On date
Show all 12 registrationsShow fewer

Kolte-Patil Integrated Townships Limited, in questions

Does Kolte-Patil Integrated Townships Limited finish projects on time?

Of 11 MahaRERA registrations whose promised completion date has arrived, 6 kept it (55%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.

How many projects has Kolte-Patil Integrated Townships Limited registered with MahaRERA?

9 projects under 12 MahaRERA registrations; 7 completed on MahaRERA.

Does Kolte-Patil Integrated Townships Limited have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology