Company or firm · first RERA registration 2017

Kohinoor Associates

Deedo IDDD-DG79

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 39 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay39 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shubham GalleriaP52100003815PimpriCertificate Signed31 Jan 202130 Oct 2022+70 mo*
Shubham GalleriaP52100045483PimpriCertificate Signed31 Mar 202631 Mar 2026+8 mo*

Kohinoor Associates, in questions

Does Kohinoor Associates finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 39 mo late. Across Maharashtra, 73% kept their date.

How many projects has Kohinoor Associates registered with MahaRERA?

1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Kohinoor Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology