Skip to content
Deedo home
Menu

Kk Associates

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shivneri SaffronP51600023238Nashik (M Corp.)2019Not reported1 Jul 2025—On date
Sahyadri HeightsP51600032479Nashik2022Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shivneri SaffronOn date
  • Sahyadri HeightsOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology