Khatri Pawar Builders And Developers
Deedo IDDD-7J3YOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 26 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Khatri Pawar Enclave Of Building B1P52100020861 | Baramati (M Cl) | Certificate Signed | 4 Nov 2022 | 4 Nov 2022 | +48 mo* |
| Khatri Pawar EnclaveP52100076703 | Baramati (M Cl) | Certificate Signed | 31 Dec 2034 | 30 Apr 2035 | +4 mo |
Khatri Pawar Builders And Developers, in questions
Does Khatri Pawar Builders And Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 26 mo late. Across Maharashtra, 73% kept their date.
How many projects has Khatri Pawar Builders And Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Khatri Pawar Builders And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.