Khalid Abdul Kadir Beban

Deedo IDDD-M955

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 47 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay47 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mariyam ApartmentP52000032553AshtamiCertificate Signed31 Dec 202231 Dec 2022+47 mo*

Khalid Abdul Kadir Beban, in questions

Does Khalid Abdul Kadir Beban finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.

How many projects has Khalid Abdul Kadir Beban registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Khalid Abdul Kadir Beban have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.