Skip to content
Company or firm · first RERA registration 2017

Kaustubh Construction Private Limited

Deedo IDDD-EVH0

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 27 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay27 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Redevlopment Of Rajendra Nagar - Shree Ganesh Chs Ltd.P51800006765BorivaliCertificate Signed31 Dec 201831 Dec 2019+12 mo
Redevlopment Of Sun And Moon Chs Ltd. Bldg No. 12 And 13P51800007374BorivaliCertificate Signed31 Dec 201930 Jun 2023+42 mo

Kaustubh Construction Private Limited, in questions

Does Kaustubh Construction Private Limited finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 27 mo late. Across Maharashtra, 73% kept their date.

How many projects has Kaustubh Construction Private Limited registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Kaustubh Construction Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology