Kaustubh Construction Private Limited
Deedo IDDD-T5ADOf 5 registrations whose promised date has arrived, 1 kept it (20%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
7 of 8 registrations with dates moved or missed their RERA date · months late against the original promise
8 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Redevlopment Of Rajendra Nagar - Shree Ganesh Chs Ltd.P51800006765 | Borivali | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Redevlopment Of Sun And Moon Chs Ltd. Bldg No. 12 And 13P51800007374 | Borivali | Certificate Signed | 31 Dec 2019 | 30 Jun 2023 | +42 mo |
| Redevelopment of Vasishtha Krupa Co-operative Housing Society Ltd.P51800030271 | Akurli | Certificate Signed | 31 Aug 2024 | 31 Aug 2025 | +12 mo |
| VanraiP51800046638 | Akurli | Certificate Signed | 31 Jul 2026 | 30 Nov 2026 | +4 mo |
| PrimroseP51800046761 | Kandivali | Certificate Signed | 31 Jul 2026 | 31 Jul 2026 | On date |
| Breeze 91P51800080406 | Borivali | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 mo |
| Kaustubh CapitalPM1181012501924 | Borivali | Certificate Signed | 30 Sep 2030 | 30 Jan 2031 | +4 mo |
| Kaustubh Park 91PR1180002503020 | Eksar | Certificate Signed | 30 Dec 2030 | 30 Apr 2031 | +4 mo |
Kaustubh Construction Private Limited, in questions
Does Kaustubh Construction Private Limited finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 1 kept it (20%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Kaustubh Construction Private Limited registered with MahaRERA?
8 projects under 8 MahaRERA registrations; 4 completed on MahaRERA.
Does Kaustubh Construction Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.