Karmabhoomi
Deedo IDDD-6CBSOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| KarmabhoomiP50500055060 | Mahalgaon | Certificate Signed | 31 Mar 2026 | 31 Jul 2026 | +8 mo* |
| Karmabhoomi-2PP1191012601682 | Mahalgaon | Certificate Signed | 31 Mar 2031 | 31 Mar 2031 | On date |
Karmabhoomi, in questions
Does Karmabhoomi finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Karmabhoomi registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Karmabhoomi have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
