Karmaa Realty
Deedo IDDD-VVNMOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 47 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Karmaa GalaxyP51600003024 | Nashik (M Corp.) | Completed | 31 Dec 2017 | — | On date |
| Karmaa Galaxy Phase 2P51600032375 | Nashik (M Corp.) | Certificate Signed | 31 Dec 2022 | 31 Aug 2023 | +47 mo* |
Karmaa Realty, in questions
Does Karmaa Realty finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.
How many projects has Karmaa Realty registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Karmaa Realty have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
