Company or firm · first RERA registration 2023
Karari Builders And Developers
Deedo IDDD-T8JTNone of 2 registrations has reached its promised completion date yet.
Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record
Delivery record
None of 2 registrations with dates has moved or missed its RERA date
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Karari AvenueP99000051609 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| Pr1240002501257PR1240002501257 | Vasai Virar City (M Corp) | Not on record | 31 Dec 2030 | — | On date |
Karari Builders And Developers, in questions
Does Karari Builders And Developers finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has Karari Builders And Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Karari Builders And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology