Company or firm · first RERA registration 2017

Karan Janhavi Development Coroporation

Deedo IDDD-7PNW

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 23 mo late.

Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay23 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Silicon Bay Phase IP52100004042VadgaonsheriCertificate Signed31 Dec 201831 Dec 2019+12 mo
Silicon Bay Phase IIP52100027850HaveliCertificate Signed31 Jan 202431 Jan 2024+33 mo*
Silicon Bay Phase IIIP52100032163VadgaonsheriCertificate Signed31 Jul 202431 Jul 2024On date

Karan Janhavi Development Coroporation, in questions

Does Karan Janhavi Development Coroporation finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.

How many projects has Karan Janhavi Development Coroporation registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Karan Janhavi Development Coroporation have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology