Karan Janhavi Development Coroporation
Deedo IDDD-7PNWOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 23 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Silicon Bay Phase IP52100004042 | Vadgaonsheri | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Silicon Bay Phase IIP52100027850 | Haveli | Certificate Signed | 31 Jan 2024 | 31 Jan 2024 | +33 mo* |
| Silicon Bay Phase IIIP52100032163 | Vadgaonsheri | Certificate Signed | 31 Jul 2024 | 31 Jul 2024 | On date |
Karan Janhavi Development Coroporation, in questions
Does Karan Janhavi Development Coroporation finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Karan Janhavi Development Coroporation registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Karan Janhavi Development Coroporation have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.