Kalpataru Construction (Pune)

Deedo IDDD-ZQTA

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 30 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay30 mowhen late · Maharashtra: 4 mo
First sales on record5registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kalpataru Estate Building 8P52100017535Pimpale GuravCertificate Signed30 Dec 202228 Jun 2025+30 mo

Kalpataru Construction (Pune), in questions

Does Kalpataru Construction (Pune) finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 30 mo late. Across Maharashtra, 73% kept their date.

How many projects has Kalpataru Construction (Pune) registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Kalpataru Construction (Pune) have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology