Company or firm · first RERA registration 2018

Kalp Buildcon And Infra

Deedo IDDD-0HEG

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 56 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay56 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kalp ResidencyP52100018344PethCertificate Signed30 Mar 202230 Mar 2022+56 mo*

Kalp Buildcon And Infra, in questions

Does Kalp Buildcon And Infra finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 56 mo late. Across Maharashtra, 73% kept their date.

How many projects has Kalp Buildcon And Infra registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Kalp Buildcon And Infra have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology