Company or firm · first RERA registration 2017
K Maniar
Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 70 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay70 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 1 ran past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Sethia GrandeurRegulatory order: PROJECT NAME:SETHIA GRANDEUR (Regulatory Case No. 197 OF 2024) dated 30 May 2024. | 30 May 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sethia GrandeurP51800009020 | Andheri | Certificate Signed | 30 Dec 2020 | 30 Jun 2022 | +70 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology