Jhv Construction Company Private Limited
Deedo IDDD-903BOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Hira Laxmi HeightsP52000002569 | Ulawe | Certificate Signed | 30 Jun 2018 | 31 Oct 2018 | +4 mo |
Jhv Construction Company Private Limited, in questions
Does Jhv Construction Company Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Jhv Construction Company Private Limited registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Jhv Construction Company Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.