Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Anant Nath Nagar CHSLP51800034363BorivaliCertificate Signed31 Mar 202531 Mar 2025On date
Anand BhawanP51800035189AndheriCertificate Signed28 Feb 202628 Feb 2026On date
Trinity TowersPR1180002500480BandraCertificate Signed31 Mar 202931 Jul 2029+4 mo

Jet Speed Realtors Private Limited, in questions

Does Jet Speed Realtors Private Limited finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Jet Speed Realtors Private Limited registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Jet Speed Realtors Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology